Saltash Waterside: New Coastal Defence Nears Completion at Jubilee Green
Around 140 metres of new rock armour has been installed along the River Tamar to protect Saltash’s waterside from coastal erosion.
In Saltash News | Local infrastructure
A major project to strengthen the riverbank at Jubilee Green in Saltash is nearing completion, following several months of construction to replace an ageing coastal defence beneath the Tamar Bridge.
An update published by Cornwall Council on 15 October 2026 confirmed that the new defence was substantially complete, with only filling work beneath sections of the footway remaining.
The scheme has replaced the deteriorating concrete revetment with approximately 140 metres of rock armour designed to protect the seawall, riverbank, boat park, public open space and car park from coastal erosion.
Why was the work needed?
The existing concrete structure was designed to protect the waterside from erosion. However, routine inspections found that it had deteriorated and reached a failing condition.
Without repairs, continued deterioration could have threatened the riverbank and the facilities beside it, including the boat park, green space and car park.
Cornwall Council’s project information explains that rock armour was selected as a durable, relatively low-maintenance solution suited to the location’s environmental and heritage sensitivities.
What has been built?

The new defence stretches approximately 140 metres along the tidal River Tamar.
Rock armour consists of large, carefully positioned stones that help absorb and break up the energy of waves. The stones are placed over a geotextile membrane and a layer of smaller material, helping stabilise the structure and reduce the risk of soil being washed away from behind it.
The rocks also create spaces that can provide shelter for marine life, including crabs, mussels, barnacles and small shellfish.
The project involves around 4,000 tonnes of rock armour, delivered to the waterside during the construction programme.
How was the work carried out?
The project was delivered by Cormac on behalf of Cornwall Council, with support from the council’s Climate Adaptation Programme.
Work began in May 2026. Contractors had to plan construction around tidal conditions, environmental requirements and the practical challenges of working beside the river.
Deliveries arrived by road from the A38 via Old Ferry Road, with stone brought in during planned periods to manage the impact on the surrounding area.
Space in the Jubilee Green car park was reduced to accommodate the site compound and materials. The project team also worked to manage disruption to residents, visitors and waterside users.
During construction, sections of the footway were closed for safety, particularly while heavy equipment was operating and repairs were being made beneath the path.
What remains to be done?
In its update dated 15 October, Cornwall Council said the main construction work was substantially complete, with filling of voids beneath sections of the footway still to be finished.
These voids had been identified during the works and required investigation and repair. The filling work is intended to stabilise the area beneath the path.
The council has not, in the update cited here, confirmed a final completion date for every remaining task or provided a separate announcement confirming that all works have since been signed off.
Residents and visitors should continue to follow any on-site signs and access restrictions.
What does this mean for Saltash?
Jubilee Green is an important part of Saltash’s waterside, used by residents, visitors and people accessing the boat park and river.
The new defence is intended to protect these facilities against ongoing coastal erosion and improve the resilience of this stretch of the waterside.
The project also highlights the maintenance challenges facing infrastructure beside a tidal river, where structures must withstand changing water levels and wave action while taking account of the area’s environmental importance.
The Tamar Tavy Estuary has protected biological and geological features, so environmental considerations formed part of the project’s planning and delivery.
The new rock armour is expected to provide a more durable defence, although no coastal protection scheme can remove every risk from erosion or extreme weather.
Where can residents find more information?
Cornwall Council’s project page contains construction updates and photographs of the new defence.
- Official project updates: Jubilee Green Coastal Defence — Cornwall Council
- Project contact: Cormac can be contacted on 0300 1234 222 or by email at contracting@cormacltd.co.uk.
The council’s latest published update identified the main construction as substantially complete, with the remaining work focused on filling beneath parts of the footway.
In Saltash News will continue to follow local infrastructure projects and report on confirmed progress, outstanding work and their impact on residents.
Sources
- Cornwall Council, Jubilee Green Coastal Defence, Saltash — official project page and 15 October 2026 update.
- CornishStuff, The 140 metres of rock now guarding Saltash’s Jubilee Green, 18 October 2026.
- Cornish Times, Saltash Waterside defence works nearing completion, 22 October 2026.